The change request shall be evaluated using the results of the impact analysis and a decision
regarding acceptance, rejection or delay shall be made by the authorized persons such as the Project manager, Safety
manager, Person in charge of quality assurance, and the D evelopers involved.
The accepted change requests can be prioritized and combined with related accepted change
requests.
If a change request is rejected, then the rationale for the rejection is captured so that it can be
documented later in the process.
This is similar to the way in a which a standard Configuration Control Board works.
|